(HBO) - Being identified as an important arterial route linking Hanoi-Northwest transport corridor, ensuring the Security and National Defense, however, since its start of construction to now, Hoa Lac – Hoa Binh Road project has had extended the deadlines for many times. Will the project continue to "be missed" with the drastic direction of Minister of Transport Nguyen Van The, which requires to complete the Road by 31st August, 2018.

Everything is going pretty quickly. Basically, the travelling road is quite convenient. The investors are directing contractors to speed up the construction items. Hoa Lac road begins to be connected with National Highway 6, the area of adjacent to Ky Son town and Trung Minh commune. Only in Ky Son district, the road of 16.32/ 25.7 km long, crossing the area of Yen Quang, Phuc Tien, Mong Hoa, Dan Ha communes and Ky Son town is being shaped. At present, there are 2 arisen places with a large volume of work, which are being implemented by investors and contractors, including: Da River water pipeline construction area, in Yen Quang commune and the construction site of ground clearance in Phuc Tien commune.

 

joint Stock Company No. 36-67 mobilizes the facilities for the last carpet of the XL 9 package.

 

Minh Duc joint Stock Company is the construction contractor from the beginning of the project, currently focusing on human resources, and construction machinery for offloading works (Can bridge) – the item arising from the adjustment of the route and sand caves belonged to Phuc Tien commune. In other packages, the contractors are organizing for the finalization of the final items. joint Stock Company No. 36-67, the construction contractor of Construction Package 9 in Yen Quang commune has mobilized dozens of trucks, floor loaders to finish the last layer of the road. Mr. Nguyen Tho Tue, the representative of Company 36-67 said: The Company is a contractor from the beginning of the project to now. There has been the information that the investors had difficulty in funding issue. However, the contractors are mobilizing the maximum of manpower and machinery to ensure the progress, quality of work as planned to hand over the project in late August.

Exchanging with contractors, we knew that: The most difficult thing is when the bank stopped disbursing to investors. If we were disbursed more money, the deadline to August 31st  for Hoa Lac - Hoa Binh Road under the direction of Minister of Transport Nguyen Van The certainly completed. Then it takes only about 50 minutes to travel from Hoa Binh to Hanoi.

 

Related Topics


PM attends groundbreaking ceremony for electronic PCB factory in Hoa Binh

Prime Minister Pham Minh Chinh attended a groundbreaking ceremony for an electronic printed circuit board (PCB) factory at Da River Left Bank Industrial Park in Hoa Binh province on April 13. The electronic PCB factory is invested by Japan's Meiko Group at a total cost of 200 million USD.

In the first quarter, the total capital of the credit institutions was estimated at 40,128 billion VND

In the first quarter of 2024, the credit institutions in the province have actively deployed the legal documents of the State and the State Bank relating to currency, credit and interest rates. At the same time, they have promoted the capital mobilization, focusing on the solutions to expand the credit investment along with strengthening the credit quality management, lending to priority programs to promptly meet the capital needs for export - business and consumer demand during Tet in 2024.

Lac Son - attractive destination for investors

Outside the key economic region of Hoa Binh, yet Lac Son district has utilised its potential and strengths regarding labour, land, and transportation connectivity to attract investment to the locality, contributing to promoting socio-economic development.

Hoa Binh accelerating disbursement of ODA, foreign concessional loans

In a move to expedite the execution and disbursement of the 2024 capital plan for ODA projects, aiming for a disbursement rate of over 90% of the allocated funding, the Hoa Binh People's Committee issued Document No. 483/UBND-KTN on April 3, 2024, regarding such efforts.

The man who promotes Kim Boi district’s fruit brand

Nguyen Van Thap from Kim Duc hamlet, Vinh Tien commune, Kim Boi district, has built the brand of Hoa Qua Son for local fruits. His efforts have brought about income for his family and generated job opportunities for locals, helping hundreds of households escape from poverty.

Q1 disbursement of public investment funds reach 15% of yearly plan

The Hoa Binh administration was entrusted by the Prime Minister with a budget of 3.43 trillion VND (142.91 million USD) for investment in 2024. The provincial People's Council approved nearly 3.76 trillion VND, which has been meticulously allocated to projects, achieving 100% of the assigned capital plan.