Taking advantage of the favorable weather,
the joint venture contractor have accelerated the construction progress of Hoa Binh Bridge 3 across Da
river, trying to inaugurate in 2019.
The project of Hoa Binh Bridge 3 belongs to phase 2 of "The Program for the Northern
Mountainous Urban - Hoa Binh City". The investor is the People's Committee
of Hoa Binh City, a partnership with Trung Chinh Trading and Construction Co.,
Ltd. and Hoang Son company is the construction contractor.
Hoa Binh Bridge 3 is designed to be
constructed of permanent pre-stressed reinforced concrete. The bridge has a
length of over 535 meters with a path of nearly 210 meters. The width of the
bridge is 16 meters, in which the lane is 12 meters in width. The total width
of the bridge is more 4 meters than that of Hoa Binh Bridge 1.
During the past time, Trung Chinh Trading and
Construction Co., Ltd - the bridge construction unit has mobilized machinery,
human resources and materials to construct the bridge abutments and has
organized construction to make 3 shifts to accelerate the construction
progress.
Up till now, the project for Hoa Binh Bridge
3 has achieved the volume of over 260 billion VND. The payment value including
the advance and payment records has reached 231 billion VND. The main items are
being concentrated to complete, the boundary on the left bank has been
completed.
At the same time, the clearance work is being
completed in rush, creating the conditions for Hoang Son Company to construct
the path as soon as possible.
It is expected that in April, 2019 the
construction units will officially implement the boundaries of Hoa Binh Bridge
3, ensuring to complete and put it into use in 2019, helping to reduce the
overloading of Hoa Binh Bridge 1 in the past time.