The provincial People’s Committee has worked to accelerate the construction of the Hoa Binh – Hanoi highway and the Hoa Binh – Moc Chau section of the Son La highway, which received in-principle approval from the provincial People’s Council in 2021.
Construction sped up for the highway section
that runs through Du sang Commune, Kim Boi district.
Kim Boi and Luong Son districts and Hoa Binh
city rushed to carry out compensation and resettlement work.
Kim Boi issued 18 decisions to retrieve 24.52
hectares of land in Du Sang, Binh Son, Vinh Tien, Dong Bac, and Vinh Dong
communes and Bo town. As much as 56.96 billion VND (2.31 million USD) was
disbursed for compensation and site clearance costs. The district also
implemented three sub-projects to develop a resettlement area in Du Sang and
Vinh Tien communes, and one in Ving Dong commune.
Meanwhile, Luong Son district approved four
decisions on land and asset compensation with a total value of 26 billion VND.
It expects to hand over around 1.5 kilometres of road in March.
As for Hoa Binh city, compensation measures for
122 households is being penned while a decision on compensation plan for
graves, land and assets on land worth 224 million VND has been approved. The
city is proposing a compensation plan for residential land and agricultural
land valued some 20 billion VND.
The management board of the local transport
projects joined hands with competent departments and sectors to remove
bottlenecks regarding land filling plans, waste disposal arrangements, changes
in forest use purposes, and moving electricity lines.
After the site clearance was completed, the
contractor carried out construction on the section connecting Kim Boi district
with Hoa Lac – Hoa Binh expressway intersection. To date, 61.08% of the
workload has been completed.
Vice Chairman of the Kim Boi district People’s
Committee Tran Tuan Son said that the construction is underway at the sites of
Chieng bridge (Vinh Dong commune), Bai Chau bridge (Dong Bac commune), Dong
Ngoai bridge (Vinh Tien commune), Kham bridge (Binh Son commune), and Chuon and
Chuon 1 bridges (Du Sang commune).
The district is working to accelerate site
clearance at the remaining three sites, he added.
The highway construction project is among the
key ones which will create a locomotive for local socio-economic development.
Therefore, the provincial People’s Committee has paid due attention to handling
roadblocks to push ahead the construction progress. Most recently, Vice
Chairman of the provincial People’s Committee Quach Tat Liem inspected the
construction progress at the sites. He asked the investors, departments,
sectors, districts and city where the highways run through to drastically
settle the site clearance work and accelerate construction for the roads.
Costumes of ethnic groups in the northern province of Hoa Binh were showcased at the Hoa Binh square in Hoa Binh city on November 17 evening as part of the Hoa Binh province’s Cultural and Tourism Week.
On the evening of November 16, the provincial authorities held a solemn ceremony at Hoa Binh City Square to receive the Certificate of National Special Relic Site for the archaeological site of Hang Xom Trai, Mai Da Lang Vanh and to open the 2024 Culture-Tourism Week of the province.
With a focus on maintaining a close contact with the people, local authorities at all levels of Hoa Binh have implemented a range of measures to ensure security and order in ethnic minority-inhabited areas, improving their legal awareness, combating crime and social vices, and contributing to maintaining political stability and social order, while promoting socio-economic development in these areas.
On November 8th, Ngai hamlet, Thach Yen commune (Cao Phong) organized the Great National Solidarity Festival in 2024. There was the attendance of Mr. Bui Van Khanh, the Deputy Secretary of the Provincial Party Committee, the Chairman Provincial People's Committee; Colonel Trinh Duc Thiem, the Commander of the Provincial Military Command...
Hoa Binh Power Company (PC Hoa Binh) has proactively rolled out plans and solutions to ensure the stable and safe operation of the electricity grid, so as to meet the increasing needs of customers in the year-end period.
To achieve the goal of becoming a new-style rural district by 2025, the authorities of Yen Thuy district are working diligently to meet various criteria, with a particular focus on developing model new-style rural residential areas and model gardens.